BusinessSaturday, November 14
GlobalFoundries broke ground on a new Malta chip plant backed by up to $21 billion
The Daily Albany team
If you live in Saratoga County, the chip boom just got bigger. GlobalFoundries broke ground Friday on a new fab at its Malta campus. It's part of a U.S.-Japan initiative that could provide up to $21 billion for two new plants at the Luther Forest Technology Campus. Japan is expected to provide about $10 billion for the first one, which GlobalFoundries expects to open in 2029. The project also gets $570 million in incentives from New York state.
The Malta expansion comes with big numbers
- $21 billion
- in possible U.S.-Japan investment for two new fabs
- 27,000
- construction and related ecosystem jobs expected
- 1,000+
- high-skilled manufacturing jobs expected
- $570 million
- in incentives awarded by New York state
Sources: WNYT.com, spectrumlocalnews.com
Todd Shimkus, president of the Saratoga County Chamber of Commerce, said the original goal was "to have three fabs on that property, and we’re about to get our second." Specialized workers coming for construction are expected to support local hotels, restaurants, retailers, contractors and other businesses. He called housing affordability one of the county's biggest challenges: the county has added about 900 units, mostly apartments.
- Current Malta fab: 400,000 wafers a year
- New first fab: about 900,000 wafers of annual capacity
- Saratoga County median home sale price: above $500,000 for the first time
Malta's chip story runs from 2008 plans to a 2029 target
- 2008Semiconductor manufacturing plans are first announced for the area.
- 2009Malta becomes home to GlobalFoundries' global headquarters.
- Nov. 13GlobalFoundries breaks ground on the first of two new fabs.
- 2028A decision on the second fab is expected before year's end.
- 2029GlobalFoundries anticipates the first new fab will begin operations.
Sources: WNYT.com, spectrumlocalnews.com
Sources: WNYT.com, spectrumlocalnews.com