Two Thruway repaving projects, including one on I-90 in Albany County, are substantially complete
The Daily Albany team
If you take I-90 between Exit 24 and Exit 25, there's fresh pavement. Two Thruway projects, on I-90 in Albany County and I-87 in Ulster County, are substantially complete, Gov. Kathy Hochul announced. The $34.7 million investment wrapped up ahead of Thanksgiving travel.
I-90 in Albany County carries far more drivers than I-87 in Ulster County
| I-90 in Albany County | Measure | I-87 in Ulster County |
|---|---|---|
| $15.8 million | Cost | $18.9 million |
| 36.6 | Lane miles repaved | 40.4 |
| 125K | Drivers a day | 42,000 |
Source: silive
The $15.8 million Albany County project repaved a stretch between Exit 24 and just west of Exit 25, and it improved the Guilderland Service Area's fuel service area. Farther south, an $18.9 million project repaved I-87 between Exit 18 in New Paltz and Exit 19 in Kingston.
- I-90 overhead sign structures: replacement expected spring 2027
- Ulster County: some pavement work continues in spring 2027
- Ulster project contractor: Callanan Industries of Albany
$34.7 millioninvested in two Thruway repaving projects covering 77 lane miles
Hochul's office said both projects were completed on time and on budget.
Source: silive
Sources: Mid Hudson News, silive